保温板的生产工艺和流程解析

来源:http://www.sdyingxu.com/news/72.html 发布时间:2017-05-26
保温板生产线操作简便,用人少,普通工人6人就可生产操作8-10台立模机,日产(24小时连班)可达到600-800㎡。还可根据需求调整改变墙体板的长度、厚度,能够满足市场各种规格的需求。
Insulation board production line has the advantages of simple operation, less people, ordinary workers can produce 6 8-10 Taiwan vertical molding machine operation, Nissan (24 hour class) can reach 600-800 square meters. In addition, the length and thickness of the wall plate can be adjusted and adjusted according to the requirements so as to meet the requirements of various specifications in the market.
保温板的生产工艺;
Process for producing insulating board;
1、上料、混合:通过上料系统将定量的水泥、发泡剂、稳泡增强剂加入搅拌机,干混30秒钟;
1, feeding, mixing: through the feeding system will be quantitative cement, foaming agent, foam stabilizer added to the mixer, dry mixing for 30 seconds;
2、搅拌:将定量的温水加入搅拌机,湿搅拌2分钟;将定量的发泡剂加入搅拌机搅拌8-15秒钟;
2, stir: add the amount of warm water into the mixer, wet stirring for 2 minutes. Add the amount of foaming agent into the blender and stir for 8-15 seconds;
3、注模、发泡:随即将浆料注入模具内发泡,发泡过程约3-5分钟;
3, injection molding, foaming: then the slurry into the mold foaming, foaming process about 3-5 minutes;
4、初期养护:注模完成后静置若干小时进行初期养护;
4, initial maintenance: after the injection mold is completed, static for several hours for initial maintenance;
5、脱模:待发泡水泥保温板完成 初凝,具备初期强度时即可脱模;
5, release: foam cement insulation board to complete the initial coagulation, with the initial strength can be released;
6、切割:具备一定强度的发泡水泥保温板毛坯脱模后即可进行切割,切割规格根据需要调整切割刀片进行;
6, cutting: a certain strength of the foam cement insulation board, blank after stripping can be cut, cutting specifications according to the need to adjust the cutting blade;
7、成品养护:发泡水泥保温板养护龄期应不低于7天。
7, product maintenance: foam cement insulation board maintenance age should be no less than 7 days.